Deep-water Line 1 of TurkStream pipeline completed
Source: Tanjug
Monday, 30.04.2018.
13:07
Comments
Illustration (Photo: nostal6ie/shutterstock.com)
Gazprom, which plans to complete the pipeline in 2019, said in a statement that 1,161 km of pipe had been laid since it began construction last year, Reuters reports
The average rate of the deep-water pipelay carried out by the pipelaying vessel Pioneering Spirit was 4.3 km/day, Gazprom says, as reported by the Russian agency Tass.
The maximum pipelaying rate – 5.6 km/day – was reached twice in February 2018.
Following the works schedule, Pioneering Spirit will continue the deep-water pipelay of Line 2 in the third quarter of 2018, Gazprom says in its press release.
The first line of the TurkStream pipeline will supply Turkey alone, whereas the second one will deliver Russian gas to south and southeast Europe.
Each line will have a capacity of 15.75 billion cubic meters of gas a year, and the total value of the project has been estimated at EUR 11.4 billion.
Companies:
Gazprom Moscow
Tags:
TurkStream
Gazprom
Black Sea
first line of TurkStream pipeline
second line of TurkStream pipeline
deep water of TurkStream pipeline
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.